Mr. Kyle Coble March 3, 2021
Construction Manager
UNC Facilities Planning & Design, Giles F. Horney Building
103 Airport Drive
Chapel Hill, NC 27599-1800
Project: LAS #10761-60 UNC School of Medicine, Neurosciences Research Building (NRB) 7th & 8th Floor
Renovations
State ID #11-09861-02G
Re: Project Closeout – Final Report
Dear Mr. Coble,
We are pleased to submit the Final Report and Record Documents for the project. The Report is structured per the
Chapter 600 requirements of the 2009 NC State Construction Manual.
We enjoyed working with you, UNC, and the School of Medicine on the project and appreciate all of the assistance
that you provided.
Sincerely,
Craig A. Carbrey, AIA
Senior Associate
Project Manager
Attachments:
Final Report
Designer Certification Documents
Contractor Closeout Documents
Design Team Record Documents
Copy:
Lauren Rockart – LAS
Project Team – Kramer Engineering Services
File: K:\PROJECTS\10761-00\CORRESPONDENCE\10761-60_UNC-NRB_Final Report_Cover Letter.docx
1450 Raleigh Road, Suite 109
Chapel Hill, NC 27517
877-929-1400
lordaecksargent.com
LAS #10761-60 UNC School of Medicine, Neurosciences Research Building (NRB) 7th & 8th Floor Renovations
State ID #11-09861-02G
FINAL REPORT
TABLE OF CONTENTS
CONTRACT DATES .......................................................................................................................................... Page 2
EXHIBIT A –
PROJECT DESCRIPTION ................................................................................................................................ Page 2
EXHIBIT B –
PROJECT COST DATA ..................................................................................................................................... Page 4
EXHIBIT C –
CHANGE ORDERS .......................................................................................................................................... Page 4
EXHIBIT D –
NAMES AND ADDRESSES OF CONTRACTOR AND PRIMARY SUBCONTRACTORS ................................ Page 5
EXHIBIT E –
ENERGY CRITERIA ......................................................................................................................................... Page 6
EXHIBIT F –
DESIGNER CERTIFICATION DOCUMENTS ................................................................................................... Page 7
EXHIBIT G –
CONSTRUCTION CLOSEOUT DOCUMENTS ................................................................................................ Page 7
ATTACHMENTS .......................................................................................................................... Following this Report
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 2
LAS #10761-60 UNC School of Medicine, Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
State ID #11-09861-02G
The Project Information is as follows:
CONTRACT DATES
Bid Opening Date November 14, 2019
Award Date
Notice to Proceed for Contractor
December 12, 2019
February 13, 2020
Begin Work Date February 17, 2020
Final Inspection Date October 27, 2020
Project Acceptance Date October 27, 2020
Warranty Expiration Date October 27, 2021
EXHIBIT A – PROJECT DESCRIPTION
Project Address: Neurosciences Research Building, 115 Mason Farm Road, Chapel Hill, North Carolina 27599-7250
*Project is part of the Mary Ellen Jones (MEJ) Renovation funding authority.
The Project consists of the limited alteration on the 7th and 8th Floors of the existing Neurosciences Research
Building (NRB) at the UNC-Chapel Hill School of Medicine (SOM). The existing building is circa 2001. The purpose
of the project is to refresh existing finishes and reconfigure existing spaces in the building to accommodate the
relocation of lab spaces and associated equipment for the Department of Dermatology from another building at the
SOM. The circulation/egress path on the floor is existing to remain. Existing exits and corridors within the work area
are shared by only one tenant and the new work does not impact egress. Additional detailed descriptions of specific
project components are as follows:
Architectural
Interior
1. The work was designed in accordance with the 2018 NC Existing Building Code for Level II Alterations.
2. The existing building is Type I-A Construction, “B” Occupancy, and is fully-sprinklered with an NFPA 13
System. The sprinkler system was modified as required for the new work.
3. The existing building is approximately 12,100 SF per floor. Approximately 6,600SF per floor is included
in the areas of work.
4. Limited work on the existing 3rd Floor was performed by UNC Shops as a separate project. The work
consisted of limited demolition, repair of existing surfaces, and installation of new finishes. The
renovated spaces on the 3rd Floor are used as new offices for Dermatology.
5. The scope of work for the primary program spaces on the 7th and 8th Floors consists of the following:
a. Lab Spaces: new power and optional standby power as required for equipment, replacement of
existing lab countertops with new epoxy resin tops, new sinks and fittings at lab benches, paint
existing walls, replace damaged ceiling tiles, clean floors.
b. Equipment Rooms: new power and optional standby power as required for equipment, new
mechanical systems for supplemental cooling, paint existing walls, clean/replace floors.
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 3
c. Research Spaces: new power and optional standby power as required for equipment, new lab
casework, new ceiling tiles, paint existing walls, clean/replace floors, new emergency showers
were added either in research spaces or adjacent corridors.
d. Shared Office Space and Private Offices: renovation of existing offices and addition of new
walls for new offices, paint walls, new carpet tiles, replace damaged ceiling tiles at existing
offices and install new ceiling tiles at new offices.
e. Break Rooms: new casework and sink, new water connections for coffee maker and
refrigerator, paint walls, clean/replace floors.
f. Bathrooms: clean floors, install new ADA-compliant auto door operators, new auto flush valves
at ADA stalls, new vertical grab bars at ADA stalls.
g. Corridors: clean floors, paint walls, replace damaged ceiling tiles, provide ADA-compliant water
coolers. New ADA compliant emergency showers were added at corridors, to support adjacent
Lab and Research spaces.
6. Interior Demolition in areas of work included: removal of existing millwork, removal of interior (non-load-
bearing) partitions, removal of interior doors and frames, partial demo of existing CMU walls for
installation of new doors and frames, removal of existing ceilings and light fixtures, and removal of
existing floor finishes, removal of mechanical components to prep for new work, removal of electrical
systems and components to prep for new work.
7. New interior work included: new metal-framed partitions and drywall, new paint, patch/repair of existing
acoustical ceiling tiles and installation of new acoustical ceiling tiles, new carpet tile flooring, new
resilient flooring, new hollow metal frames, new doors and hardware, new millwork, new lab casework
and lab fittings, new toilet accessories, and preparation and repair of existing surfaces (to remain) that
were impacted by new work.
Exterior
1. This project consisted of interior renovations only. No modifications were made to the exterior as part of
this project.
Structural
Foundations
1. This project consisted of interior renovations only. No modifications were made to the existing
foundations as part of this project.
Super Structure
2. No modifications were made to the existing super structure as part of this project.
Fire Protection
1. Replaced sprinkler heads and modified branch piping as needed to accommodate the new plan layout,
new ceiling heights and finishes, lights, and other ceiling-mounted devices.
2. Pendant and upright sprinklers were installed.
3. The installation was in accordance with NFPA 13 Ordinary Hazard Group 1, occupancy classification.
Plumbing
1. Modifications to existing plumbing system to accommodate the new program.
2. Extended cold water to valve boxes for a coffee makers and refrigerator connections.
3. Selective demolition of some lab sinks, lab gas outlets and associated piping was completed.
4. Several new lab sinks, break room sinks, and emergency fixtures were installed.
5. Air and vacuum piping was extended to biosafety cabinets.
6. CO2 gas piping was extended between gas cylinders and CO2 incubators. Switching manifolds were
installed at cylinder locations.
HVAC
1. Existing terminal reheat boxes, air valves, and controls remained.
2. Distribution ductwork, downstream of terminal reheat boxes, was modified in some areas to
accommodate new ceilings.
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 4
3. Exhaust hoods were installed above tissue processors and stainers in the Grossing Lab.
4. The fume hood in the Grossing lab was removed and the dedicated fume hood exhaust was re-
purposed for the grossing stations.
5. An existing fume hood riser and fan which provided general exhaust was connected to a new fume hood
in the Procedure Room.
6. Supplemental cooling units utilizing building process chilled water were installed in equipment rooms
with high cooling loads.
7. All 7th and 8th floor spaces were rebalanced and controls were recalibrated.
Electrical
1. Electrical work involved the renovation of various spaces on the 7th and 8th floors. To the greatest
extent possible the existing lighting, normal power and telecom serving these spaces remained as is.
An admin area on each floor was mostly renovated including new lighting.
2. Normal Power - The existing normal power system remained with a dedicated panel in each lab space.
3. Optional Standby Power – The optional standby power system for the renovated spaces was reworked
such that many lab spaces received a dedicated 120/208V panel, located in the corridor. The system
predominantly serves refrigeration and other lab equipment. This allows these and other spaces to have
circuits added and reworked in the future without the need for shutting down or affecting other rooms. A
new 75kVA dry type transformer and associated 120/208V, 250A distribution panel for serving these
panels was located on each floor. Metering was provided at each distribution panel such that future
addition to the system can be more easily determined.
4. Emergency Power – Due to the fact that the existing system was a hybrid emergency/optional standby
power system, and present codes require separation of emergency and optional standby power, a new
separate emergency power infrastructure system was provided. The system consists of a new
emergency ATS (automatic transfer switch), and panel to serve emergency lights and other required
emergency loads.
5. Lighting – For the most part existing lighting remained. Where new lighting is required dimmable LED
troffers have been provided.
6. Fire Alarm – Minor alterations to the existing fire alarm system were made to adapt to the renovation.
7. Telecommunication – For the most part the existing voice/data telecom system remained. Where
required a system of hardwired telecom outlets and wireless access points have been provided for the
voice/data telecom system. The system consists of outlets served by conduit from the outlet to a cable
tray in the corridor.
EXHIBIT B – PROJECT COST DATA
Contracts1 Original Contract Fee Change
Orders/Amendments
Subtotal
General Construction $1,576,600.00 $161,584.27 $1,738,184.27
Design Contract –
Planning & Programming
$19,690.00 $0 $19,690.00
Design Contract – Const
Documents & CA
$180,260.00 $61,900.00 $242,160.00
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 5
Total Contract $1,776,550.00 $223,484.27 $2,000,034.27
1The NRB Renovation is part of the Mary Ellen Jones (MEJ) Renovation enabling projects, and project funding is through MEJ.
The Contract Amounts indicated in the Project Cost Data are specific to NRB and do not account for other MEJ project totals.
EXHIBIT C – CHANGE ORDERS
UNC Change Order
(CO) Number
Change Order
Proposals (COP)
Included in CO
Description Amount
Change Order #1 001 Demo & replace existing flooring in office area $9,129.00
002 Provide Electrical Add Alternates 3 and 4 $47,400.00
003 Demo wall above existing ceiling $1,702.00
004R2 Install mixing valves at eyewashes $8,919.00
005 Door height price adjustment $2,012.27
006-1 Flooring repair $2,539.00
007 Provide and install LCN closers $37,358.00
008 Remove existing steel beams from 7104, 8104,
8122, and 8122A
$2,304.00
009 Plumbing revisions per PR-008 $3,519.00
010 User Group changes per PR-005 $9,882.00
011R HVAC changes per PR-007 $11,077.00
012 Additional shelving supports $1,743.00
013 Stainless steel sink at 8th Floor Break Room $716.00
014 VCT infill and VCT Flooring replacement $2,278.00
015 Electrical Changes per PR-011 $5,178.00
Total CO#1 $145,756.27
Change Order #2 016 Sprinkler changes per PR-014 $2,231.00
017 Additional fire alarm work per PR-009 $731.00
018 Deduct Change Order per PR-012 ($948.00)
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 6
019 Additional labor and materials per PR-013 $936.00
020R Resin top and sink in Room 8117 $5,485.00
021R Third Party UL Labeling of Grossing Stations $5,848.00
022 Re-work ceilings at electrical panel locations $1,545.00
Total CO#2 $15,828.00
Total - All CO’s $161,584.27
EXHIBIT D – NAMES AND ADDRESSES OF CONTRACTOR AND PRIMARY SUBCONTRACTORS
General Contractor:
H.M. Kern Corporation 160 Thatcher Road Greensboro, NC 27409
Subcontract or Material Name of Contractor or Supplier Address
Demolition Subcontractor 360 Services and Demolition 206 Waycross Road
Fayetteville, NC 28312
Millwork Subcontractor AMG Casework 10315 Chapel Hill Road
Morrisville, NC 27560
Lab Casework and Lab
Equipment Subcontractor
Nycom, Inc. 606 Church Street, Suite 101
Morrisville, NC 27560
Doors, Frames & Hardware
Supplier
Schiller 4500 Green Point Dr., Suite 105
Greensboro, NC 27410
Auto Door Operators Jacobs Glass Company 4915 Hillsborough Road
Durham, NC27705
Glass and Glazing DGC Glass Systems, LLC 5025 Departure Drive, Suite 103
Raleigh, NC 27616
Framing, Drywall & Insulation
Subcontractor
White’s Metal Stud & Drywall 3450 Gum Springs Church Road
Pittsboro, NC 27312
Ceilings Trinity Custom Interiors PO Box 1987
Fuquay Varina, NC 27526
Flooring Subcontractor Brock Contract Services 1400 Nowell Rd.
Raleigh, NC 27607
Painting Subcontractor E. Caligari & Son, Inc. 1333 Ingleside Road
Norfolk, VA 23502
Mechanical (HVAC) Contractor:
Arnold Service Company 820 Person Street Fayetteville, NC 28301
Electrical Contractor:
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 7
JC Electric, Inc. 3430 Coates Industrial Blvd, Suite
100
Durham, NC 27705
Plumbing Contractor:
Hockaday Mechanical Corporation 3717 Auburn Church Road Garner, NC 27529
Sprinkler/Fire Protection Contractor:
Sunland Fire Protection, Inc. 1218 Elon Place High Point, NC 27263
EXHIBIT E – ENERGY CRITERIA
The building is existing to remain and the scope of the work is primarily interior improvements. Per NC Energy Code
Section 101.4.1: existing systems that were lawfully in existence prior to the renovation can remain. New
components added to the building, including Mechanical and Electrical system modifications, were installed per the
requirements of the 2018 NC Energy Conservation Code using the Prescriptive Performance Method. Sheet G031 of
the Record Documents Package outlines additional information pertaining to the Energy Summary.
EXHIBIT F – DESIGNER CERTIFICATION DOCUMENTS
a. SCO Certificate of Completion: executed copy included with Attachments
b. SCO Certificate of Compliance: executed copy included with Attachments
EXHIBIT G – CONSTRUCTION CLOSEOUT DOCUMENTS
a. Contractor’s Affidavit of Release of Liens: executed copy included with Attachments
b. Contractor’s Affidavit of Payment of Debts and Claims: executed copy included with Attachments
c. Final Pay Application which includes the Final MBE Documentation: executed copy included with
Attachments
ATTACHMENTS
Copies of the following documents are attached, after Page 8 of the Report.
SCO Certificate of Completion
SCO Certificate of Compliance
HM Kern Corporation Hold Harmless and Warranty Documents from HM Kern Corporation
Final Pay Application which includes the Final MBE Documentation
Record Documents - Project Specifications
Record Documents - Project Drawings (As-Built)
Copy:
LAS Project Team
Kramer Engineering Services
LAS #10761-60 UNC School of Medicine. Neurosciences Research Building (NRB), 7th & 8th Floor Renovations
Page 8
File: K:\PROJECTS\10761-00\CCA\CloseOut\10761-60_UNC-NRB_Final Report.docx
March 2009
SECTION 324
SCO CERTIFICATE OF COMPLIANCE;
PROJECT:
UNC School of Medicine, Neurosciences
Research Building (NRB), Renovations to
the 7th and 8th Floors
LOCATION: UNC Chapel Hill, School of Medicine
115 Mason Farm Road, Campus Box 7250,
Chapel Hill, NC 27599-7250
BUDGET CODE:
ITEM:
SCO PROJECT ID:
11-09861-02G
OWNER: The State of North Carolina through the University of North Carolina at Chapel
Hill
TYPE OF CONTRACT: General Contract
FINAL AMOUNT: $1,738,184.27
DATE OF FINAL ACCEPTANCE: October 27, 2020
CONTRACTOR: H.M. Kern Corporation
I (we) certify that the work on the above-referenced project has been inspected in
accordance with Chapter 133, Article 1, of the General Statutes, and that:
(1) The inspections of the construction, repairs or installations have been
conducted with the degree of care and professional skill and judgment ordinarily exercised
by a member of my (our) profession; and
(2) to the best of my (our) knowledge, and in my (our) professional opinion as an
architect or engineer, the contractor has fulfilled the obligations of such plans,
specifications and contract.
Signed this 18th day of February_2021.
Designer Signature (SEAL)
Lauren Dunn Rockart
Designer Name
Principal
Discipline/Title
March 2009
SECTION 326
SCO CERTIFICATE OF COMPLETION;
PROJECT:
UNC School of Medicine,
Neurosciences Research Building
(NRB), Renovations to the 7th and
8th Floors
LOCATION:
UNC Chapel Hill, School of
Medicine
115 Mason Farm Road, Campus
Box 7250, Chapel Hill, NC 27599-
7250
BUDGET CODE:
ITEM:
SCO PROJECT ID: 11-09861-02G
DATE: November 2, 2020
OWNER: The State of North Carolina through the University of North Carolina at
Chapel Hill
DESIGNER:
Lord Aeck Sargent, A Katerra
Company, LLC
PRIME CONTRACTOR:
-
CONTRACTOR: H.M. Kern Corporation
I (we) certify that all work on the above referenced project has been completed
according to the plans, specifications, addenda and approved change orders and
that the project is ready for owner occupancy.
The final inspection was made on October 27, 2020. The guarantee period
begins on October 27, 2020, and shall terminate on October 20, 2021.
The contractors report that final payments have been made to all material
suppliers, employees and subcontractors, and copies of their lien waivers are
attached.
Builder's risk insurance was cancelled as of October 28, 2020, and a copy of the
cancellation notice is attached hereto.
The total time for completion as allowed in the contract plus granted time
extensions is two hundred fifteen (215) days. The actual time required for
completion was two hundred fifty-three (253) days, and the contractor is not
liable for liquidated damages. The contractor(s) has (have) been notified of any
proposed assessments of liquidated damages. Copies of each notification and
my (our) letter of recommendations as to the amount of liquidated damages are
attached.
Copies of the following items are attached as indicated below:
Written guarantees:
March 2009
Affidavits:
__________________________________________________________
Contractor’s Affidavit of Release of Liens: Provided
Contractor’s Affidavit of Payment of Debts and Claims: Provided
_____________________________________________________________
Consent of Surety Company to Final Payment: Provided
Final Report: Provided
Electronic As-built drawings: Provided
Other required closing papers of the contractor: Included with Contractor’s
Closeout Attachments
___________________________________________________________
_______
There are no unsettled disputes between the owner and contractor, owner and
designer, or the designer and contractor at this time.
Signed this 18th day of February_2021.
____________
(SEAL)
____________________
Designer Signature
Lauren Dunn Rockart
Designer Name
Principal
Title
PROJECT INFORMATION
PROJECT
UNC School of Medicine – Neurosciences Research Building 7th &
8th Floors for Dermatology
SCO #11-009861-02G | UNC CIP #501
115 Mason Farm Road
Chapel Hill, NC 27599
GENERAL CONTRACTOR
H.M. Kern Corporation HMK Project # 926
160 Thatcher Road
Greensboro, NC 27409
(P) 336-668-3213
Akers Hill, ahill@hmkern.com
ARCHITECT
Lord Aeck Sargent, a Katerra Company, PLLC LAS #10761-00
1450 Raleigh Road, Suite 109
Chapel Hill, NC 27517
(P) 877-929-1400
Craig Carbrey, ccarbrey@lordaecksargent.com
ENGINEER
Kramer Engineering Services, LLC
5517 Cascade Dr.
Chapel Hill, NC 27514
(P) 919-933-3360
Donna Kramer, donna@kespllc.com
PROJECT INFORMATION
Contract Date: January 9, 2020
Substantial Completion: October 28, 2020
Insurance Cancellation: October 29, 2020
Brief Project Description
Renovation of the vacant lab spaces on the 7th floor (6,629 SF) and 8th floor
(6,624 SF) of the Neurosciences Research Building to create spaces for the
Dermatology Department.
School of Medicine – Neurosciences Research Building 7th & 8th Floor
SCO #11-009861-02G
SUBCONTRACTOR LISTING
Company:
Address:
Phone:
Contact:
360 Services and Demolition
206 Waycross Road
Fayetteville, NC 28312
910-797-2520
Steve Ludwig, sludwig@360servicesanddemolition.com
Scope: Section 024100- Demolition
Company:
Address:
Phone:
Contact:
AMG Casework
10315 Chapel Hill Road
Morrisville, NC 27560
919-462-9203
Valerie Moody, valerie@amgcasework.com
Scope: Section 064100- Custom Cabinets and Woodwork
Company:
Address:
Phone:
Contact:
Arnold Service Company
820 Person Street
Fayetteville, NC 28301
910-425-3350
Scott McGowan, scott@ascheatandair.com
Scope: Division 23- Heating, Ventilating and Air-Conditioning
Company:
Address:
Phone:
Contact:
Brock Contract Services
PO Box 33415
Raleigh, NC 27636
919-570-1300
Scout Brock, sbrock@brockcontract.com
Scope: Section 090561- Preparation of Concrete to Receive Adhesively Installed Flooring
Section 096010- Flooring Transitions, as pertaining to 096500 & 096800
Section 096500- Resilient Flooring
Section 096800- Carpet
Includes Moisture and pH Testing
Company:
Address:
Phone:
Contact:
E. Caligari & Son, Inc.
1333 Ingleside Road
Norfolk, VA 23502
757-853-4511
Jeff Hamele, jeff@cp1896.com
Scope: Section 079000- Joint Sealers, as pertaining to 099100
Section 099100- Paints and Coatings
School of Medicine – Neurosciences Research Building 7th & 8th Floor
SCO #11-009861-02G
Company:
Address:
Phone:
Contact:
Hockaday Mechanical Corporation
PO Box 26685
Raleigh, NC 27611
919-773-2008
Bob Carter, bob@hmcor.com
Scope: Division 22- Plumbing
Company:
Address:
Phone:
Contact:
Jacobs Glass Company
4915 Hillsborough Road
Durham, NC 27705
919-383-1120
Paul Walker, paul@jacobsglass.com
Scope: Section 084229- Automatic Entrances
Company:
Address:
Phone:
Contact:
JC Electric, Inc.
4900 Hillsborough Road
Durham, NC 27705
919-309-9000
Rick Coates, rickcoates@jcenc.com
Scope: Division 26- Electrical
Division 27- Communications
Division 28- Electronic Safety and Security
Company:
Address:
Phone:
Contact:
Nycom, Inc.
606 Church Street, Suite 101
Morrisville, NC 27560
919-957-9545
Robert McCullough, rmccullough@nycominc.com
Scope: Section 115300- Laboratory Equipment
Section 115313- Laboratory Fume Hoods
Section 123553- Laboratory Casework
Company:
Address:
Phone:
Contact:
Sunland Fire Protection, Inc.
PO Box 277
Jamestown, NC 27282
336-886-7027
Rick Rye, rick.rye@sunlandfire.us
Scope: Division 21- Fire Suppression
Company:
Address:
Phone:
Contact:
Triangle Maintenance & Janitorial Service
2020 Winston Diamond Ct
Raleigh, NC 27610-5775
919-633-9667
Henry Singletary, trimaint@gmail.com
Scope: Final Cleaning
School of Medicine – Neurosciences Research Building 7th & 8th Floor
SCO #11-009861-02G
Company:
Address:
Phone:
Contact:
Trinity Custom Interiors
PO Box 1987
Fuquay Varina, NC 27526
704-985-3742
Nan Salmon, nan@trinitycustominteriors.com
Scope: Section 090510- Ceiling Coordination, as pertaining to 095100
Section 095100- Suspended Acoustical Ceiling
Company:
Address:
Phone:
Contact:
White’s Metal Stud & Drywall
3450 Gum Springs Church Road
Pittsboro, NC 27312
919-542-0638
Scott White, whitesdrywallnc@gmail.com
Scope: Section 090510- Ceiling Coordination, as pertaining to 090610 & 092116
Section 090610- Partition Schedule
Section 092116- Gypsum Board Assemblies
SUPPLIER LISTING
Company:
Address:
Phone:
Contact:
DGC Glass Systems, LLC
5025 Departure Drive, Suite 103
Raleigh, NC 27616
919-500-4700
Matt Radford, mradford@dgcgs.com
Scope: Section 088000- Glazing
Company:
Address:
Phone:
Contact:
Martin Architectural Products, Inc.
511 E Chatham Street
Cary, NC 27511
919-469-9661
Vanessa Eason, veason@mapdoors.biz
Scope: Toilet Accessories per Contract Documents
Toilet Partition Hardware per Contract Documents
Company:
Address:
Phone:
Contact:
Schiller Architectural Hardware
4500 Green Point Drive, Suite 105
Greensboro, NC 27410
336-234-3747
Jonathan Tudor, jtudor@goschiller.com
Scope: Section 081100- Steel Doors and Frames
Section 081416- Flush Wood Doors
Section 087100- Door Hardware
827 Gum Branch Road
Jacksonville, NC 28540
(910) 455-7576
(800) 682-7741 toll free
www.siagroup.com
October 29, 2020
H.M. Kern Corporation
160 Thatcher Road
Greensboro, NC 27409
Owner: University of NC at Chapel Hill
103 Airport Drive
Chapel Hill, NC 27599
Project Name: UNC School of Medicine – Neurosciences Research Building – 7th & 8th Floors for Dermatology
SCO#11-009861-02G
115 Mason Farm Road
Chapel Hill, NC 27599
To Whom It May Concern:
Please be advised that SIA Group is the insurance agency for H. M. Kern Corporation.
It is our understanding that the above referenced project has a Substantial Completion date of October 28 2020. We are
requesting H. M. Kern Corporation report to the Builders Risk insurance carrier that this project has been completed and
delivered for occupancy; therefore, coverage will be terminated for this project by the insurance carrier.
If you should need anything further, please advise. Thank you.
Sincerely,
Charlene Heubach
Charlene Heubach CPCU AAI AU AINS AIC AU-M APA
Account Manager
SIA Group
1333 Ingleside Road, Norfolk, VA 23502-1914
Phone: 757-853-4511 Fax: 757-855-9424
Website: www.ecaligariandson.com
10/27/2020
HM Kern
Project Name: UNC NRB
Location: Chapel Hill, NC
Gentlemen:
This is to certify that the joint sealer applied directly to UNC NRB Project is hereby
guaranteed for a five-year period against bubbling, chipping or peeling. This
guarantee is to be in force for a period of one year from the date of substantial
completion of building and full material replacement shall be made should this
replacement be necessary as a result of a defect in our materials and labor only.
This guarantee does not cover damage resulting from settling of building, major
building movements, efflorescence, or mechanical or external physical causes or
failure of previous paint coatings.
The statements herein reflect the complete liability of E. Caligari & Son, Inc. and
there are no other warranties expressed or implied.
Very truly yours,
E. CALIGARI & SON, INC.
Richard G. Gerloff
President
Jeff Hamele
Project Manager
Schiller Architectural Hardware
UNC Neuroscience Bldg
115 Mason Farm Road
Chapel Hill, NC,27599
CONTRACTOR: HM Kern Corporation
160 Thatcher Rd
Greensboro, North Carolina, United States
27409
ARCHITECT: Lord Aeck Sargent
1450 Raleigh Road
Suite 109
Chapel Hill, NC,
27517
Prepared By: Jonathan Tudor
Schiller - Greensboro
4500 Green Point Dr, Suite 105
Greensboro, NC, 27410
Date:
Revision Date 10.17.2018
LIMITED LIFETIME WARRANTY
VTI Architectural Products, Inc. (“VT”) warrants that all flush wood doors manufactured by VT (“Doors”) shall be free from defects
in materials and workmanship from the date of purchase from VT, subject to the following terms, conditions, tolerances and
exclusions.
The owner’s sole and exclusive remedy against VT shall be limited to repair or replacement of Doors determined to be defective or
refund of the purchase price of the defective Doors only as determined by VT in its sole discretion. Should any Door become
defective after being properly installed, VT will assess each situation and determine on a case-by-case basis whether it will pay any
amount to remove, refinish and/or reinstall the Door. However, VT will not be liable for any removal, refinish and/or reinstallation
costs when any defect is apparent prior to the original installation of the Door. Inspection of the Doors must be made upo n receipt by
owner and any claim must be received by VT within thirty (30) days after discovery of the defect(s). Failure to so notify VT shall fully
and completely relieve VT from any obligation under this warranty. VT shall not be liable for any Doors re paired or replaced without
its prior written approval.
Record this information in case of claims
Customer _________________________________________________________________________________
Project _________________________________________________________________________________
Location _________________________________________________________________________________
VT Order # _________________________________________________________________________________
Door Type(s) _________________________________________________________________________________
TOLERANCES
1. Stile, rail and show-through (telegraphing) on doors shall not be considered a defect unless the faces of the door vary
from a true plane in excess of 1/100 inch in any three-inch span.
2. Warp shall not be considered a defect unless it exceeds 1/4” in the plane of the door itself. Warp is any distortion in the
door itself, and does not refer to the relation of the door to the frame or jamb in which it is hung. For doors 1-3/4” or thicker,
warp will not exceed 1/4” in doors 3’-6” x 7’-0” or smaller; nor will it exceed 1/4” in any 3’-6” or 7’-0” section of larger
doors. For doors less than 1-3/4” thick, warp will not exceed 1/4” in doors 3’-0” x 7’-0” or smaller. Warp is measured by
placing a straightedge on the concave face and determining the maximum distance from straightedge to door face.
3. Action on any claim for warping or for telegraphing may be deferred, at the option of VT, for a period of time not to
exceed 12 months from the date of claim, If a door has been installed prior to such claim, the door must remain in the
original hung installation during the period of deferment to permit conditioning of the door to humidity and temperature.
EXCLUSIONS
1. Unsatisfactory service or appearance caused by failure to follow the “Handling, Job Finishing and Installation
Instructions” set forth below.
2. The appearance of field finished doors.
3. The appearance of doors with high gloss, transparent, or opaque finishes; or otherwise unorthodox finishes.
4. Natural variations in the color, texture, character or cut of the wood.
5. The warranty against warp does not apply to the following:
Revision Date 10.17.2018
a. Doors with different face materials or veneer grain configurations on opposite sides of the door.
b. Doors that are improperly installed or do not swing freely.
c. Warp on doors less than 1-3/4” thick but larger than 3’-0” x 7’-0”.
d. Appliques on one face of the door only, creating an unbalanced condition.
e. Applied mouldings exceeding 3-1/2” wide or covering more than 25% of the door face.
6. This warranty does not cover doors with:
a. Cutouts for lights (lites) and/or louvers, any edge of which is nearer than 5” to any edge of the door.
b. Cutouts having less than 3-5/16” on non-rated & 20-minute fire doors, and less than 5” on 45-, 60-, and 90-minute fire
doors between adjacent cutouts for unit locks, closures, or other hardware cutouts on flush doors; and cutouts having less
than 1-1/2” on stile and rail doors and on non-rated SCL core flush doors.
7. Cracking of high pressure decorative laminate faced doors with openings cut by other than the manufacturer or its
authorized representative. Radius of 1/4” at corners of openings must be maintained.
8. Door accessories, supplied by the manufacturer, for a period exceeding one year.
9. Doors altered by others.
10. Normal wear and tear, including wear-through of the finish, or deterioration for reasons other than material and
workmanship of the door itself.
11. Incompatibility of hardware with a particular door construction.
12. Doors where self-tapping or combination metal/wood screws are used to attach surface-applied hardware.
13. Interior doors used in an exterior application. An exterior opening is defined as an opening that cannot be climate
controlled for temperature and/or humidity on both sides.
14. Acoustical doors requiring hardware other than standard locks and hinges.
15. In order not to induce warp or excessive deterioration of your door, avoid using dark stains or paints on the door surfaces
exposed to direct sunlight. Doors painted any dark color with exposure to sunlight will not be warranted.
16. Placement quantity or size of knots that are manufactured from any “knotty” species are not covered under the terms of
this warranty.
17. Supa Collection or EnVivo Collection Doors.
HANDLING, JOB FINISHING AND INSTALLATION INSTRUCTIONS
Refer to VT USEFUL JOBSITE brochure online at www.vtindustries.com/ujs.
NO OTHER WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, ARE MADE, INCLUDING, BUT NOT LIMITED
TO MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE OR NON-INFRINGEMENT. UNDER NO
CIRCUMSTANCES SHALL VT BE LIABLE FOR ANY LOSS OR DAMAGE ARISING FROM THE PURCHASE, USE
OR INABILITY TO USE ITS PRODUCTS, OR FOR ANY SPECIAL PUNITIVE, INDIRECT, INCIDENTAL, OR
CONSEQUENTIAL DAMAGES. NO DEALER, DISTRIBUTOR, FABRICATOR, INSTALLER, AGENT OR EMPLOYEE
OF VT HAS THE AUTHORITY TO ADD TO OR MODIFY THE OBLIGATIONS OR LIMITATION OF THIS
WARRANTY. THIS WARRANTY SHALL BE INTERPRETED EXCLUSIVELY UNDER THE LAWS OF THE
STATE OF IOWA. VT RESERVES THE RIGHT TO REVISE OR TERMINATE THIS WARRANTY AT ANY
TIME. ONLY DOORS PURCHASED FROM THE EFFECTIVE DATE OF THIS WARRANTY THROUGH
THE DATE OF ANY REVISION OR TERMINATION OF THIS WARRANTY WILL BE COVERED BY THIS
WARRANTY.
Schiller Architectural Hardware
UNC Neuroscience Bldg
115 Mason Farm Road
Chapel Hill, NC,27599
CONTRACTOR: HM Kern Corporation
160 Thatcher Rd
Greensboro, North Carolina, United States
27409
ARCHITECT: Lord Aeck Sargent
1450 Raleigh Road
Suite 109
Chapel Hill, NC,
27517
Prepared By: Jonathan Tudor
Schiller - Greensboro
4500 Green Point Dr, Suite 105
Greensboro, NC, 27410
Date:
Page 7 of 8
AP
R
I
L
2
0
1
5
Door hardware warranties
Commercial
Product type Brand Series Warranty
period
Locks & latches
Legge Tubular Latches & Bolts, Night latch, G2, 950, 990MF,
995MF 10 year
Schlage A, AL, B250, B500, CL1000, D, ND, Brass padlocks
Cylinders & keying Schlage Cylinders (excluding keys)10 year
Door furniture
Legge 67, 500, 700, 800, 4000, 5300, 5400, 6000, 8000 10 year
Schlage 7000, 9000 10 year
Entrance handles Legge 1100, 1200 10 year
Door controls
(Closers, Floor springs
& Transom closers)
LCN 1461, 1460T/1461T, 4020T ST, 4031, 4031T, 4041XP,
4041XPT 30 year
LCN 3130, 6030 15 year
Briton 1120, 1130, 2800, 5000, 7500 10 year
LCN 4040SME, 4310ME 2 year
Door controls
(Ancillary hardware)
Briton 3000 selectors
10 yearIves7253 Pivot set, COR coordinators, FB40 Auto Flush bolts
Glynn Johnson 450 Overhead stops/holders
Exit devices
Briton 372E, 376E, 377E, 378E, 379E
10 year
Von Duprin
22, 2227, 33A, 3327A, 88, 8827, 99, 9927
ALK Alarm kit, EL Electric Latch retraction 1 year
General hardware
Legge
Pull handles & push plates, 13000 Hinge, Special hinge
sets, Barrel bolts, Chain bolts, Restrictor chains, Flush
bolts, Panic bolts, Indicator bolts, Catches, Handrail
suppports, Doorstops & hooks
10 year
Schlage Sliding cavity locks, Door stops, Roller catches, Door
viewers 10 year
AP
R
I
L
2
0
1
5
Allegion (“Company” or “Seller”) warrants its products to be free from defects in material and workmanship for the
stated periods above from the date of purchase. The Company will, at its option, repair or replace any products which
in the opinion of the Company are found to be defective, provided said products are returned to Allegion, freight
prepaid. The Company reserves the right to inspect the installation of defective products before any removal and
return of any such products.
This warranty excludes deterioration of decorative finishes, unless those finishes are specifically listed in the product
warranty.
Additional exclusions or conditions applicable to the warranty are as follows:
(a) The warranty shall not cover any defect or damage which may be caused or partly caused by or arise through:
i) Failure on the part of the Buyer to properly install or maintain any Goods; or
ii) Failure on the part of the Buyer to follow any instructions or guidelines provided by the Seller; or
iii) Any use of any Goods otherwise than for any application specified on a quote or order form accepted
by Seller; or
iv) The continued use of any Goods after any defect becomes apparent or would have become apparent
to a reasonably prudent operator or user; or
v) Fair wear and tear, or any accident or act of God.
vi) The warranty shall cease and the Seller shall thereafter in no circumstances be liable under the terms
of the warranty if the Goods are repaired, altered or overhauled without the Seller’s consent.
vii) In respect of all claims the Seller shall not be liable to compensate the Buyer for any delay in either
replacing or repairing the Goods or in properly assessing the Buyer’s claim.
(b) For Goods not manufactured by the Seller the warranty shall be the current warranty provided by the
manufacturer of Goods, if any, and to the extent that such warranty can be transferred by Seller to Buyer.
(c) No other warranties, express or implied, are made with respect to the products or services including, but
not limited to, any implied warranty of merchantability or fitness for a particular purpose.
This warranty does not exclude, restrict or modify any statutory rights.
Allegion shall in no event be liable for any incidental or consequential damages for breach of any warranty.
Warranty terms and conditions
MI-Line Installation and Service Manual (1003362 Rev. C) Page 8
Section 1
Medical Illumination International, Inc.
Limited Warranty
This document comprises the general terms of your product’s Limited Warranty. By accepting the
shipment of the product, the owner/purchaser agrees to adhere to the warranty terms and
conditions expressed herein.
Medical Illumination International, Inc. (“Medical Illumination”) Lighting Equipment is warranted
against defective material and/or workmanship, excluding normal replacement parts (e.g.
sterilizable handles), for a period of three (3) years from the date of shipment. This Limited
Warranty applies exclusively to the repair or replacement of parts recognized as defective by
Medical Illumination that are in normal use and have not been modified or repaired by
unauthorized personnel.
This Limited Warranty extends only to the first retail purchaser of a product, and is not transferable
or assignable. This warranty supersedes all other guarantees or warranties, expressed or implied.
WARRANTY SERVICE & REPAIRS
Medical Illumination does not provide (or give any compensation for) outside repair services or field
labor. Therefore, in the event of a failure covered under this warranty, please take the following
immediate action:
1. Contact Medical Illumination via phone at (818) 838-3025, through our website at
http://www.medillum.com, or by facsimile at (818) 838-3725.
A. Be prepared to give the model number, serial number, and full description of the failure.
B. Our Customer Service department will attempt to solve the problem over the phone. If it
becomes necessary to send the product to the factory for repair, you will be provided with a
Return Authorization number. Products sent to the factory without a Return Authorization
number will not be accepted.
2. It is the retail purchaser’s obligation to arrange for shipment return of a product to the factory for
warranty service, which shall be at the retail purchaser’s expense. Carefully package the light
component (light head, arm assembly, mount assembly, etc.) and return it, freight prepaid and
insured, with the Return Authorization number clearly marked on the outside of the box, to:
Medical Illumination
547 Library Street
San Fernando, CA 91340
RMA#______
When returning product for repair, damage resulting from inadequate packing is not covered by
this warranty. In addition, shipping insurance does not cover damage due to inadequate packing.
We recommend that the package be insured against loss or in-transit damage. Medical Illumination
cannot be held responsible for in-transit loss or damage. In the event that freight-related damage
should occur, Medical Illumination will notify you immediately so that you can file a damage claim
with the proper freight carrier.
MI-Line Installation and Service Manual (1003362 Rev. C) Page 9
Section 1
Medical Illumination
Limited Warranty (cont’d)
Within the aforementioned time period of three (3) years from date of shipment, Medical
Illumination will evaluate the returned product, repair as appropriate, and ship the product back to
you with freight costs prepaid by the Company. In the event that non-warranty damage or failure is
discovered, you will be contacted before any repairs are performed.
EXCLUSIONS
This Limited Warranty does not cover the following:
• Any field labor or outside services (electricians, contractors, installation services, routine
maintenance or other repair services)
• Damage to the product resulting from tampering, accident, abuse, negligence, alteration, or
other causes unrelated to problems with material and/or workmanship
• Damage due to improper installation, use, cleaning or maintenance, as outlined in the
Installation and Service Manual for the product
• Labor costs associated with removing, re-packaging for shipment or reinstalling product
PRODUCT RETURNS:
Please contact the authorized dealer from whom the product was purchased to inquire about a
product return. Additional terms and conditions set by the dealer may apply for any returned items.
SHIPMENT DAMAGE:
If the initial shipment of your purchased product arrived in damaged condition, please leave the
packaging and its contents intact and contact Medical Illumination immediately.
Disposal of Waste
This product must not be disposed of with your other waste. Instead, it is your responsibility to
dispose of your waste equipment by handing it over to a designated collection point for the
recycling of waste electrical and electronic equipment, or by returning it to Medical Illumination
International, Inc for reprocessing. The separate collection and recycling of your waste
equipment at the time of disposal will help to conserve natural resources and ensure that it is
recycled in a manner that protects human health and the environment. For more information
about where you can drop off your waste equipment for recycling, please contact your local
city office, your waste disposal service, or your product distributor or retailer.
WARRANTY STATEMENT
PROJECT NAME:
UNC School of Medicine Neurosciences Research Building
Renovations to the 7th & 8th Floors
SCO ID # 11-09861-02G
PROJECT LOCATION: 115 Mason Farm Road, Chapel Hill, NC 27599
EFFECTIVE DATE: 10-27-20
TO WHOM IT MAY CONCERN:
PLEASE BE ADVISED THAT WE WERE THE: ELECTRICAL CONTRACTOR
FOR THE ABOVE CAPTIONED PROJECT. WE GUARANTEE OUR
WORKMANSHIP, EQUIPMENT AND MATERIAL TO
BE FREE FROM DEFECTS FOR A PERIOD OF ONE YEAR
FROM DATE OF SUBSTANTIAL COMPLETION SHOWN
ABOVE.
CONTRACTOR'S NAME: JC Electric Inc.
CONTRACTOR'S ADDRESS: 3430 Coates Industrial Blvd.
Suite 100
Durham, NC 27705
PHONE: 919-309-9000 FAX: 919-309-9927
SIGNED:
Rick Coates, Vice President, JC Electric Inc.